问题:

[单选]

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A . independentresource
B . individualworkload
C . workmilestone
D . workpackage

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.() Strongmatrix。 Projectized。 Projectcoordinator。 Weakmatrix。 You are working on the cost budget for one project. Which of the following is true() This process assigns cost estimates to project activities including risks and contingency plans.。 The cost baseline will be used to measure variances and future project performance.。 This process assigns cost estimates for expected future period operating costs.。 The cost baseline is the expected cost for the project.。 An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity? 根据《中华人民共和国船舶及其有关作业活动污染海洋环境防治管理规定》,海事管理机构收到货物适运申报、船舶适载申报后,应当根据规定的条件在()内作出批准或者不批准的决定。 24h。 48h。 72h。 7天。 Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by() executive IT manager。 projectmanger。 change control board。 projectsponsor。

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

参考答案:

  参考解析

本题暂无解析