问题:

[填空题] 公文处理必须遵循()的规范。

问题:

[单选]  The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

costaggregation。reserve analysis。parametricestimating。funding limit reconciliation。

问题:

[单选] () is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype

milestone。deliverable。etc。BAC。

问题:

[单选] () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

controls。baselines。projectstakeholders。projectmanagers。

问题:

[单选] () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

projectacceptance。scopeverification。scopedefinition。WBS Creation。

问题:

[单选] ()means that every project has a definite beginning and a definite end.

Projectphase。Unique。Temporary。Closure。

问题:

[单选] The()defines the phases that connect the beginning of a project to its end.

schedule。project life cycle。temporary。milestone。

问题:

[单选] The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

Planning。Executing。Monitoring and Controlling。Closing。

问题:

[单选] The()provides the project manager with the authority to apply organizational resources to project activities.

project management plan。contract。project human resource plan。projectcharter。

问题:

[单选] The()describes, in detail, the project's deliverables and the work required to create those deliverables.