问题:

[单选]

You are working on the cost budget for one project. Which of the following is true()

A . This process assigns cost estimates to project activities including risks and contingency plans.
B . The cost baseline will be used to measure variances and future project performance.
C . This process assigns cost estimates for expected future period operating costs.
D . The cost baseline is the expected cost for the project.

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance. Benchmarking。 Quality metric。 Quality checklist。 Brainstornung。 根据《中华人民共和国船舶及其有关作业活动污染海洋环境防治管理规定》,燃油供受单证应当包括()。 ①受油船船名; ②船舶识别号或国际海事组织编号; ③作业时间、地点; ④燃油供应商的名称、地址和联系方式; ⑤燃油种类、数量、密度和含硫量; ⑥燃油加载计划。 ①②③④。 ①②③⑤。 ①②③④⑤。 ①②③④⑤⑥。 Contract closeout is a process that involves() Customer satisfaction analysis and final payment。 Administrative closeout and archiving records。 Finial contractor payment and Lessons learned。 Product verification and administrative closeout。 Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method. Benefitcontribution。 Expertjudgment。 Scoringmodels。 Flowcharting。 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() independentresource。 individualworkload。 workmilestone。 workpackage。

You are working on the cost budget for one project. Which of the following is true()

参考答案:

  参考解析

本题暂无解析