[单选]

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A . executive IT manager
B . projectmanger
C . change control board
D . projectsponsor

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method. Benefitcontribution。 Expertjudgment。 Scoringmodels。 Flowcharting。 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() independentresource。 individualworkload。 workmilestone。 workpackage。 Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool. RationalClearcase。 QualityFunctionDeployment。 VisualSourceSafe。 ConcurrentVersions System。 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. activity duration estimating, schedule developing, activity resource estimating。 activity resource estimating, activity duration estimating, schedule development。 schedule developing, activity resource estimating, activity duration estimating。 activity resource estimating, schedule developing, activity duration estimating。 The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables. subdividing。 assessing。 planning。 integrating。

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

参考答案:

  参考解析

本题暂无解析

在线 客服