问题:

[单选]

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

根据《中华人民共和国船舶及其有关作业活动污染海洋环境防治管理规定》,燃油供受单证应当包括()。 ①受油船船名; ②船舶识别号或国际海事组织编号; ③作业时间、地点; ④燃油供应商的名称、地址和联系方式; ⑤燃油种类、数量、密度和含硫量; ⑥燃油加载计划。 ①②③④。 ①②③⑤。 ①②③④⑤。 ①②③④⑤⑥。 Contract closeout is a process that involves() Customer satisfaction analysis and final payment。 Administrative closeout and archiving records。 Finial contractor payment and Lessons learned。 Product verification and administrative closeout。 In which form of projects origination would the project manager be likely to exercise the most control over Project resources.() Strongmatrix。 Projectized。 Projectcoordinator。 Weakmatrix。 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level() independentresource。 individualworkload。 workmilestone。 workpackage。 Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool. RationalClearcase。 QualityFunctionDeployment。 VisualSourceSafe。 ConcurrentVersions System。

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

参考答案:

  参考解析

本题暂无解析

在线 客服