问题:

[单选]

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A . Strongmatrix
B . Projectized
C . Projectcoordinator
D . Weakmatrix

A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives. program。 portfolio。 projectoflargesize。 PMO。 Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance. Benchmarking。 Quality metric。 Quality checklist。 Brainstornung。 根据《中华人民共和国船舶及其有关作业活动污染海洋环境防治管理规定》,燃油供受单证应当包括()。 ①受油船船名; ②船舶识别号或国际海事组织编号; ③作业时间、地点; ④燃油供应商的名称、地址和联系方式; ⑤燃油种类、数量、密度和含硫量; ⑥燃油加载计划。 ①②③④。 ①②③⑤。 ①②③④⑤。 ①②③④⑤⑥。 An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity? Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method. Benefitcontribution。 Expertjudgment。 Scoringmodels。 Flowcharting。

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

参考答案:

  参考解析

本题暂无解析