[单选]

The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.

A . agreed-to
B . agree-to
C . agree-to-do
D . agree-with

Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work. reviewing。 estimating。 auditing。 expecting。 《中华人民共和国船舶及其有关作业活动污染海洋环境防治管理规定》,自()起施行。 2011年2月1日。 2011年1月1日。 2012年2月1日。 2012年1月1日。 Define Activities is the process ofidentifying the specific actions to be performed toproduce the() projectelements。 work drafts。 workpackage。 projectdeliverables。 Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. qualityplanning。 qualityassurance。 qualityperformance。 quality control。 The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria. work performance information。 scope statement。 changerequests。 process analysis。

The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.

参考答案:

  参考解析

该题的关键词为"compatible, shared understanding",其主要的语句结构为"The result of this analysis and dialog(主语)is(谓语)an____set of requirements(表语)",含义为"分析和讨论对应的结果为一组什么的需求",根据题意,应该是达成一致的需求集,所以从选项中识别短语,判断短语的正确形式,此处应该选择agreed-t0。agree with表示同意某人,agree to表示同意某事,此处的"同意"作为形容词性质出现,所以应该使用agreed to形式,其他都不对。