Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

A . qualityplanning
B . qualityassurance
C . qualityperformance
D . quality control

Define Activities is the process ofidentifying the specific actions to be performed toproduce the() projectelements。 work drafts。 workpackage。 projectdeliverables。 During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary. proceedings。 controls。 forecastings。 Prelibations。 The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements. agreed-to。 agree-to。 agree-to-do。 agree-with。 The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not() executedin。 inspectedin。 check-in。 look-in。 Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken. Project。 project management team。 performingorganization。 customer。

Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

参考答案:

  参考解析

该题的关键词为"monitoring specific project results. comply with relevant qualitystandards. eliminate causes ofunsatisfactory results",其语句结构为"Performing______(主语)involves(谓语)monitoring specific project results",含义为"执行什么包括监督特定的项目结果",再结合关键词分析,正是质量控制的特征,应该选择选项D。