当前位置:高级信息系统项目管理师题库>专业英语题库

问题:

[单选] Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

PERT。Resourceleveling。Schedulecompression。Critical chain method。

问题:

[单选] Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

executive IT manager。projectmanger。change control board。projectsponsor。

问题:

[单选] Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

RationalClearcase。QualityFunctionDeployment。VisualSourceSafe。ConcurrentVersions System。

问题:

[单选] Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

independentresource。individualworkload。workmilestone。workpackage。

问题:

[单选] Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

Benefitcontribution。Expertjudgment。Scoringmodels。Flowcharting。

问题:

[单选] An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

问题:

[单选] You are working on the cost budget for one project. Which of the following is true()

This process assigns cost estimates to project activities including risks and contingency plans.。The cost baseline will be used to measure variances and future project performance.。This process assigns cost estimates for expected future period operating costs.。The cost baseline is the expected cost for the project.。

问题:

[单选] In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

Strongmatrix。Projectized。Projectcoordinator。Weakmatrix。

问题:

[单选] Contract closeout is a process that involves()

Customer satisfaction analysis and final payment。Administrative closeout and archiving records。Finial contractor payment and Lessons learned。Product verification and administrative closeout。

问题:

[单选] Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

Benchmarking。Quality metric。Quality checklist。Brainstornung。