问题:

[单选]

() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

A . projectacceptance
B . scopeverification
C . scopedefinition
D . WBS Creation

The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements. Planning。 Executing。 Monitoring and Controlling。 Closing。 The()defines the phases that connect the beginning of a project to its end. schedule。 project life cycle。 temporary。 milestone。 根据《中华人民共和国船海员外派管理规定》,海员外派机构与境外船东签订的船舶配员服务协议,应当符合国内法律、法规和相关国际公约的要求,并至少包括以下()内容。 ①工资福利待遇及其支付方式; ②正常工作时间、加班、额外劳动和休息休假; ③船舶适航状况及船舶航行区域;境外船东为外派海员购买的人身意外、疾病保险和处理标准; ④社会保险的缴纳。 ②③④。 ①②。 ①③④。 ①②③④。 () is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype milestone。 deliverable。 etc。 BAC。 根据《中华人民共和国船海员外派管理规定》,海员外派机构与境外船东签订的船舶配员服务协议,应当符合国内法律、法规和相关国际公约的要求,并至少包括以下()内容。 ①海员外派机构及境外船东的责任、权利和义务; ②包括外派船员的数量、素质要求,派出频率,培训责任,外派机构对船员违规行为的责任分担等; ③外派海员的工作、生活条件; ④协议期限和外派海员上下船安排。 ①②④。 ①③④。 ①②③。 ①②③④。

() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

参考答案:

  参考解析

该题的关键词为"obtaining the stakeholders' formal acceptance、 verifying the scope",其语句结构为" (主语)1S(谓语)the process of obtaining the stakeholders' formal acceptance ofthe completed project scope",含义为"什么过程是为已完成的项目范围获取干系人的正式验收",选项B对项目的范围进行验证,其他选项容易排除。