The()defines the phases that connect the beginning of a project to its end.

A . schedule
B . project life cycle
C . temporary
D . milestone

The()describes, in detail, the project's deliverables and the work required to create those deliverables. The()provides the project manager with the authority to apply organizational resources to project activities. project management plan。 contract。 project human resource plan。 projectcharter。 根据《中华人民共和国船海员外派管理规定》,海员外派机构与境外船东签订的船舶配员服务协议,应当符合国内法律、法规和相关国际公约的要求,并至少包括以下()内容。 ①外派船员跟踪管理; ②突发事件处理; ③外派海员遣返; ④外派海员伤亡处理; ⑤特殊情况及争议处理,违约责任。 ②③④⑤。 ①②③④。 ①②③。 ①②③④⑤。 ()means that every project has a definite beginning and a definite end. Projectphase。 Unique。 Temporary。 Closure。 () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily. projectacceptance。 scopeverification。 scopedefinition。 WBS Creation。

The()defines the phases that connect the beginning of a project to its end.

参考答案:

  参考解析

该题的关键词为"phases",其语句结构为"______(主语)defines(谓语)the phases",含义为"什么定义了项目的多个阶段",通过筛选首先排除A和C,选项D也容易排除,因为Milestone(里程碑)只是关键点上发生的活动,不具备阶段的持续性特点,因而只能选择选项B。

在线 客服