当前位置:高级信息系统项目管理师题库>专业英语题库

问题:

[单选]

The()provides the project manager with the authority to apply organizational resources to project activities.

A . project management plan
B . contract
C . project human resource plan
D . projectcharter

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period. Plannedvalue。 Earned value。 Actualcost。 Costvariance。 PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. Finish-to-Start。 Finish-to-Finish。 Start-to-Start。 Start-to-Finish。 The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities. estimating。 defining。 planning。 sequencing。 The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements. Planning。 Executing。 Monitoring and Controlling。 Closing。 The()defines the phases that connect the beginning of a project to its end. schedule。 project life cycle。 temporary。 milestone。

The()provides the project manager with the authority to apply organizational resources to project activities.

参考答案:

  参考解析

该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。

在线 客服