问题:
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A . activity duration estimating, schedule developing, activity resource estimating
B . activity resource estimating, activity duration estimating, schedule development
C . schedule developing, activity resource estimating, activity duration estimating
D . activity resource estimating, schedule developing, activity duration estimating
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
● 参考解析
本题暂无解析