问题:

[单选]

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.

A . analyze
B . track
C . level
D . extend

The Unified Modeling Language is a standard graphical language for modeling object-oriented software()can show the behavior of systems in terms of how objects interact with each other. Classdiagram。 Componentdiagram。 Sequencediagram。 Use case diagram。 ()is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes. Method。 Polymorphism。 Inheritance。 Encapsulation。 The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate. Challenge。 Exploit。 Avoid。 Enhance。 Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars. milestone。 baseline。 quality。 work。 Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work. reviewing。 estimating。 auditing。 expecting。

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.

参考答案:

  参考解析

该题的关键词为"project schedule、 baseline",其主要的语句结构为一个定语从句结构"project schedule that (主语)can serve as (谓语)a baseline to_progress",含义为"项目进度可以作为怎么样项目进展的基线",根据题意,容易判断对项目进度进行跟踪,所以选择选项B。