问题:

[单选]

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

A . Riskldentification
B . Quantitative RiskAnalysis
C . Qualitative RiskAnalysis
D . Risk Monitoring and Control

Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. qualityplanning。 qualityassurance。 qualityperformance。 quality control。 The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria. work performance information。 scope statement。 changerequests。 process analysis。 The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not() executedin。 inspectedin。 check-in。 look-in。 根据《防治船舶污染海洋环境管理条例》,船舶处置污染物,应当在相应的记录簿内如实记录。船舶应当将使用完毕的船舶垃圾记录簿在船上保留()年;将使用完毕的含油污水、含有毒有害物质污水记录簿在船上保留()年。 2/3。 1/3。 2/2。 1/3。 ()is a category assigned to products or services having the samefunctional use but different technical characteristics. Itisnotsameasquality. Problem。 Grade。 Risk。 Defect。

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

参考答案:

  参考解析

该题的关键词为"analyzes the effect of risk, numerical rating",其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语)and assigns(并列谓语)anumerical rating to those risks(并列宾语)",含义为"什么过程分析风险事件的后果,并且为这些风险指定数值级别",容易判断题目描述的是量化风险分析的特点,应该选择选项B。

在线 客服