问题:

[单选] 运用动态控制原理控制施工成本的步骤中,第一步应做的工作是()。

A . 按照成本控制的要求收集施工成本的实际值
B . 找出偏差
C . 施工成本的逐层分解
D . 定期对施工成本的计划值和实际值进行比较

Company.com environment consists of 10 volume groups and 4 physical networks. The customer  Desires the fastest possible fallover for a two-node cluster.  Which of the following configuration alternatives will provide the fastest fallover?()    IPAT via IP Aliasing,default shared volume groups。  IPAT via IP Replacement default shared volume groups。  IPAT via IP Aliasing,enhanced concurrent volume groups。  IPAT via IP Replacement,enhanced concurrent volume grou。 以下业务不属于“收入”会计要素的有()。 租赁房屋取得收入。 出售企业原材料取得收入。 出售企业闲置不用设备取得收入。 企业提供维修劳务取得收入。 A researcher needs to regularly analyze large quantities of data.  They are interested in putting together a cluster of 16 UDB EEE partitions of four processors each for their data mining environment.  Each UDB partition needs to be approximately 15 rPerf.  Which of the following solutions would best fit their performance needs?() p655 4-way nodes。 p655 8-way nodes。 p5-570 4-way nodes。 p5-570 8-way node。 Companycom has five LPARs, but only one CD drive. How should the CD drive be shared among all the users without system administrator action?() Allocate the CD to the VIO Server and NFS export the CD to the user LPARs。 Allocate the CD to one of the user LPARs and config the VIO Server to NFS import it。 Allocate the CD to the VIO Server and the LPARs will share it as a Virtual SCSI device。 Allocate the CD to one of the user LPARs and NFS export it to the remaining user LPAR。 体育与健康课程目标主要有:()、()、()三部分组成。 运用动态控制原理控制施工成本的步骤中,第一步应做的工作是()。
参考答案:

  参考解析

本题暂无解析

在线 客服