[单选] 下列不属于实施性施工进度计划的是()。

A . 施工总进度计划
B . 月施工季度计划
C . 旬施工进度计划
D . 周施工进度计划

Which of the following is used to invoke a Web service from an unmanaged client?()   JAX-WS dispatch API。  Deployment descriptor。  @Resource annotation。  @WebServiceRef annotation。  Service and Interface classe。 A system administrator has just finished upgrading a system to AIX 5.2. If there are future problems, the system administrator would like to add an entry to the AIX errorlog to record this event. Which of the following commands can be issued for this purpose?() /usr/bin/errmsg "System upgraded to AIX 5.2"。 /usr/bin/errlog "System upgraded to AIX 5.2"。 /usr/bin/errupdate "System upgraded to AIX 5.2"。 /usr/bin/errlogger "System upgraded to AIX 5.2"。 自创无形资产的成本是由创造该项资产所耗费的()和活劳动费用构成的。 物化劳动。 简单劳动。 复杂劳动。 抽象劳动。 Which of the following commands will clear all software entries in the error log?() errpt -d S。 errclean 0。 errclear -d S 0。 errclean -d S 0。 对F8型制动机进行单车紧急制动试验时,制动管的减压量为()。 100kPa。 120kPa。 140kPa。 170kPa。 下列不属于实施性施工进度计划的是()。
参考答案:

  参考解析

本题暂无解析

在线 客服