问题:

[单选] 建设工程施工过程,可能会出现不利的地质条件(如地勘未探明的软弱层)而使施工进度延误、成本增加,这种风险属于()。

A . 经济与管理风险
B . 组织风险
C . 工程环境风险
D . 技术风险

若企业某产品的经营状况正处于盈亏临界点,则表明该产品销售利润率等于零。 发生水循环停滞时,上升管中的进水量() 等于零。 大于零。 小于零。 简述《癸丑报灾》的前因后果。 企业总体战略又称为() 经营战略。 竞争战略。 业务层战略。 SBU战略。 As a senior administrator at Cer-tech .com, you manage a server named ERA1 that runs Windows Server2008. It has the Windows SharePoint Services (WSS) role installed in a standalone mode.You also manage another server called ERA2. For a big project, you install WSS role on ERA2. You indicate duringthe installation that the ERA2 must be the member of a WSS server farm. But you are unable to connect toERA1 in the WSS server farm. What should you do to configure both ERA1 and ERA2 in the WSS serverarm?() reduce the Microsoft .NET Framework Trust Level to Low on both ERA1 and ERA2。 Reconfigure the Web Management Service on ERA1。 Set the Microsoft .NET Framework Trust Level to High on both ERA1 and ERA2。 Uninstall the WSS on ERA1 and select the server farm mode while reinstalling it.。 None of the above。 建设工程施工过程,可能会出现不利的地质条件(如地勘未探明的软弱层)而使施工进度延误、成本增加,这种风险属于()。
参考答案:

  参考解析

建设工程的工程环境风险包括:自然灾害、岩土地质条件和水文地质条件、气象条件、引起火灾和爆炸的因素等。本题中,不利的地质条件属于工程环境风险。

在线 客服