问题:

[多选] 关于总价合同的说法,正确的有()

A . A.采用固定总价合同,双方结算比较简单,但承包商承担了较大的风险
B . B.发包人能更容易,更有把握地对项目进行控制
C . C.固定总价合同适用于工程结构和技术复杂的工程
D . D.在固定总价合同中,承包人承担工程量风险主要是人工费上涨
E . E.由于承包人的失误导致投标报价计算错误,合同总价不予调整

简述学习动机的种类。 孟子在《万章下》中说:颂其诗,读其书,不知其人,可乎?是以论其世也。是尚友也。这里的‚‛其人‛是指() You work as the enterprise exchange administrator at TestKing.com. TestKing.com makes use of Microsoft Exchange Server messaging solution. The TestKing.com network consists of a single ActiveDirectory domain named testking.com. TestKing.com is configured to run in an Exchange Server 2010 environment. You have received instructions from the CIO to minimize the amount of e-mail messages for company executives, which areusally sent to the distribution groups. What should you do?() The best option is to include sharing policies in the plan.。 The best option is to include Outlook Protection Rules in the plan.。 The best option is to include custom MailTips in the plan.。 The best option is to include dynamic distribution groups in the plan.。 简述影响药物作用的主要因素。 职业生涯规划是一个过程,这个过程包括哪些内容()。 设计方案。 绘制具体实施图。 设置目标。 研究可行性。 关于总价合同的说法,正确的有()
参考答案:

  参考解析

采用固定总价合同,双方结算比较简单,但是承包商承担较大风险,因此本题选A选项;采用总价合同,发包单位能更容易、更有把握地对项目进行控制,因此本题选B选项;固定总价合同适用于工程结构和技术简单、风险小的工程,故C选项错误;在固定总价合同中,合同总价一次包死,固定不变,在这类合同中承包商承担了价格风险,如报价计算错误、漏报项目、物价和人工费上涨等。工作量风险有工程量计算错误、工程范围不确定、工程变更或者由于设计深度不够造成的误差等。故D选项错误,选择E选项。

在线 客服