问题:

[单选]

某工程采用工程量清单计价招标,工程量清单挖土方的工程量为2600m3,投标人甲根据其施工方案估算的挖方量为4400m3,人、材、机费为76000元,管理费为18000元,利润为8000元,不考虑其他因素,则投标人填报的综合单价应为()元/m3

A . 36.15
B . 29.23
C . 39.23
D . 23.18

优先股的股利可视为() You are the administrator of an Active Directory domain. All servers run Windows Server 2003. All client computers run Windows XP Professional. A server named Filesrv1 contains confidential data that is only available to users in the human resources (HR) department.  You want all computers in the HR department to connect to Filesrv1 by using an IPSec policy. You assign the Server (Request Security) IPSec policy to Filesrv1. Using Network Monitor, you notice that some computers in the HR department connect to Filesrv1 without using the IPSec policy.   You need to configure Filesrv1 to ensure that all computers connect to it by using the IPSec policy.   What should you do?() Assign the Secure Server(Require Security) IPSec policy.。 Assign the Client (Respond Only)IPSec policy.。 Unassign the Server(Request Security IPSec policy.。 Restart the IPSec Services service.。 简述强化的程序? Photoshop中模糊渐变是工具选项栏中提供了五种渐变的方式。 Photoshop中使用魔棒工具可生成浮动的选区。

某工程采用工程量清单计价招标,工程量清单挖土方的工程量为2600m3,投标人甲根据其施工方案估算的挖方量为4400m3,人、材、机费为76000元,管理费为18000元,利润为8000元,不考虑其他因素,则投标人填报的综合单价应为()元/m3

参考答案:

  参考解析

综合单价=(人、材、机费+管理费+利润)/清单工程量=(76000+18000+8000)/2600=39.23元/m3

在线 客服