[单选] 除合同另有约定外,承包人的人员和施工设备应全部撤离施工场地的时间是()。

A . 工程竣工验收合格时
B . 工程接收证书颁发后的56d内
C . 竣工清场后
D . 缺陷责任期满时

You create a Microsoft ASP.NET application by using the Microsoft .NET Framework version 3.5.  The application must redirect the original URL to a different ASPX page.  You need to ensure that the users cannot view the original URL after the page is executed. You also need to ensure that each page execution requires only one request from the client browser. What should you do? () Use the Server.Transfer method to transfer execution to the correct ASPX page.。 Use the Response.Redirect method to transfer execution to the correct ASPX page.。 Use the HttpContext.Current.RewritePath method to transfer execution to the correct ASPX page.。 Add the Location: new URL value to the Response.Headers collection. Call the Response.End() statement. Send the header to the client computer to transfer execution to the correct ASPX page.。 在中性点不接地或经高阻抗接地的低压电网中,当发生单相金属性接地时,中性点对地电压为()。 0。 相电压。 线电压。 大于0小于相电压。 外伤作用力方向的判定 作为一名职员,应当如何进行职业锚的自我开发()。 培养提高抉择能力。 提高取业适应性。 制定人力资源发展规划。 借助组织职位表,迭择职业目标。 埋弧焊有哪些冶金特点? 除合同另有约定外,承包人的人员和施工设备应全部撤离施工场地的时间是()。
参考答案:

  参考解析

本题涉及的考点是竣工清场。除合同另有约定外,缺陷责任期满时,承包人的人员和施工设备应全部撤离施工场地。

在线 客服