当前位置:水利水电工程综合练习题库

问题:

[问答题]

某水电站工程,经批准的施工进度计划网络图如下图所示

施工中发生了以下事件:
事件1:A工作因设计变更停工10d;
事件2:B工作因施工质量问题返工,延长工期7d;
事件3:E工作因建设单位供料延期,推迟3d施工;
事件4:在设备管道安装气焊作业时,火星溅落到正在施工的地下室设备用房聚氨酯防水涂膜层上,引起火灾。
在施工进展到第120天后,施工项目部对第110天前的部分工作进行了统计检查。
统计数据见下表:

计算截止到第110天的合计BCWP值。

下列关于发展标准参照的测验题叙述错误的是() ["发展标准参照的测验题是指根据作业目标和教学内容进行测验的命题工作","编制测验时,应注意评价的目的是学生是否已经掌握了所需要的技能","编制测验时,还要看他们是否记住了教学材料","测验的编制和评价应该采取标准参照评价的原则"] How  can  a  directory  named  /dirl  be  excluded  during  a  restore  of  files backed  up  by  name  with  the  backup command() ["By using the restore -x option followed by \/dirl","By adding an entry in the \/etc\/restore.exclude file","By using the restore -i option to enter interactive mode and executing the command:delete \/dirl","By using the restore -i option when running restore to specify a text file containing ’\/dirl1 as one of the  lines in it"] 食物中钙含量水平高时可引起铅的吸收量增加,并引起铅中毒。 Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?() ["Loadleveler","AIX Workload Manager","Partition Load Manager","Tivoli Provisioning Manager"] The INV_HISTORY table is created using the command: You would like to store the data belonging to the year 2006 in a single partition and issue the command: What would be the outcome of this command? () [" It executes successfully, and the transition point is set to '1-apr-2006'."," It executes successfully, and the transition point is set to '15-apr-2006'."," It produces an error because the partitions specified for merging are not adjacent."," It produces an error because the date values specified in the merge do not match the date values stored in the table."]

某水电站工程,经批准的施工进度计划网络图如下图所示

施工中发生了以下事件:
事件1:A工作因设计变更停工10d;
事件2:B工作因施工质量问题返工,延长工期7d;
事件3:E工作因建设单位供料延期,推迟3d施工;
事件4:在设备管道安装气焊作业时,火星溅落到正在施工的地下室设备用房聚氨酯防水涂膜层上,引起火灾。
在施工进展到第120天后,施工项目部对第110天前的部分工作进行了统计检查。
统计数据见下表:

计算截止到第110天的合计BCWP值。
参考答案:

  参考解析

本题暂无解析