当前位置:二建建设工程施工管理综合练习题库

问题:

[多选] 在各种计划方法中,()的工作进度线与时间坐标相对应。

A . A.形象进度计划
B . B.横道图计划
C . C.双代号网络计划
D . D.单代号搭接网络计划
E . E.双代号时标网络计划

You are the network administrator for your company. The network consists of a single Active Directory domain. All servers run Windows Server 2003. An administrator named Misty Shock attempts to perform troubleshooting tasks on a file server. However, when she attempts to open the security event log, she receives the error message shown in the exhibit. (Click the Exhibitbutton.) You need to ensure that Misty can complete her troubleshooting tasks. What should you do?() Add Misty's user account to the Server Operators domain group.。 Add Misty's user account to the local Administrators group on the file server.。 Configure Misty's client computer to enable the IPSec Server (Request Security) policy.。 Assign Misty's user account the Allow logon through Terminal Services user right for the file server.。 生物学死亡期() 能复苏。 血压下降。 细胞死亡。 抽搐。 为什么要控制气门间隙? 国际贸易单证通常用于处理进出口货物的()。 交付。 运输与保险。 检验检疫。 报关。 结汇。 Your company has an Active Directory forest that contains client computers that run Windows  Vista and Windows XP.     You need to ensure that users are able to install approved application updates on their  computers.     Which two actions should you perform() Set up Automatic Updates through Control Panel on the client computers.。 Create a GPO and link it to the Domain Controllers organizational unit. Configure the GPO to automatically search。 Create a GPO and link it to the domain. Configure the GPO to direct the client computers to the Windows Server Up。 Install the Windows Server Update Services (WSUS). Configure the server to search for new updates on the Inter。 在各种计划方法中,()的工作进度线与时间坐标相对应。
参考答案:

  参考解析

横道图用于小型项目或大型项目子项目上,或用于计算资源需要量、概要预示进度,也可用于其他计划技术的表示结果,横道图计划表中的进度线(横道)与时间坐标相对应,这种表达方式较直观,易看懂计划编制的意图。双代号时标网络计划是以水平时间坐标为尺度编制的双代号网络计划,兼有网络计划与横道计划的优点。

在线 客服