问题:

[单选] 施工成本控制的步骤是()。

A . 比较―分析―预测―纠偏―检查
B . 预测―检查―比较―分析―纠偏
C . 检查―比较―分析―预测―纠偏
D . 分析―检查―比较―预测―纠偏

著名经济学家特里芬讲过一个“媳妇煮粥”的故事:从前有个媳妇,贤淑能干。后来婆婆让她主持家务,负责给全家人煮粥。由于每年打的粮食很有限,然而这一家却年年添丁进口,为了让全家人都吃饱,媳妇只好不断往锅里加水,结果是粥越来越稀。最后,婆婆怀疑媳妇把米偷着背回了娘家,一气之下,将她赶出了家门。结合所学判断这个故事最有可能指的是()。 大国沙文主义。 国家垄断资本主义。 布雷顿森林体系。 经济全球化趋势。 You are the administrator of your company’s network. A user named Lilly prints dozens of documents daily from her Windows 2000 Professional computer. Lilly reports that she receives a dialog box announcing that each print job she sends has printed successfully. Lilly’s default printer is a shared printer that is connected to a Windows 2000 Server computer. She wants to have this notification turned off because she prints so many documents.  What should you do?() In the server properties of the Printers system folder, clear the Notify when remote  documents are printed option。 In the server properties of the Printers system folder, clear the Notify computer, not user,  when remote documents are printed option。 In the default printer properties, select the Ports tab, and clear the Enable bi-directional  support option 。 In the default printer properties, select the Advanced tab, and clear the Advanced printing  features optio。 两段招标实质上是一种公开招标和邀请招标综合起来的招标方式,也称为两段竞争性招标。 信息化项目是指在特定()、()、()等约束下,以应用信息技术为目标的一系列动。 在CO2超临界萃取中,目标产物的分离方法主要有等压分离,等温分离,()。 施工成本控制的步骤是()。
参考答案:

  参考解析

在确定了施工成本计划之后,必须定期地进行施工成本计划值与实际值的比较,当实际值偏离计划值时,分析产生偏差的原因,采取适当的纠偏措施,以确保施工成本控制目标的实现。其步骤如下:(1)比较;(2)分析;(3)预测;(4)纠偏;(5)检查。

在线 客服