A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?() ["Define the production partitions' maximum CPU to the licensing limitations. Define the development\/test partition maximums to one core. Configure each partition to be capped.","Define the production partitions' maximum CPU to the licensing limitations. Define the development\/test partition maximums to one core. Configure each partition to be uncapped.","Define the production partitions' maximum CPU to the licensing limitations. Define the development\/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day.","Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing."]
主观评定法
ou have a large amount of historical data in a flat file. Some analysts in your organization need to query thisdata in the file. The file is too large to load the data in it into your current database. Which is the most effectivemethod to access this data in your database() ["Use the database link.","Use the SQL*Loader utility.","Use the Oracle Data Pump utility.","Create an external table and leave the data in the flat file"]
某房地产开发公司兴建住宅楼工程。招标文件规定,工程为砖混结构,5层,工期265日,固定总价合同模式。至投标阶段工程施工图设计尚未全部完成。在此过程中发生如下事件:
事件一:施工单位中标价格为1350万元。但是经双方3轮艰苦谈判,最终确定合同价为l200万元,并据此签订了施工承包合同。
事件二:在投标过程中,某施工单位未到现场进行勘察,认为工程结构简单并且对施工现场、周围环境非常熟悉,另外考虑工期不到一年,市场材料价格不会发生太大的变化,于是按照企业以往积累的经验编制标书。
事件三:部分合同条款中规定:l.施工单位按照开发公司批准的施工组织设计组织施工,施工单位不承担因此引起的工期延误和费用增加责任。
2.开发公司向施工单位提供场地的工程地质和主要管线资料,供施工单位参考使用。事件三中合同条款有哪些不妥之处?说明正确做法。