[单选] 施工单位编制分部(分项)工程施工组织设计和季、月、旬施工计划的依据是()。

A . 施工组织总设计
B . 单位工程施工组织设计
C . 单项工程施工组织设计
D . 分部(分项)工程施工组织设计

咬接余量为咬缝宽度的()倍一般是复合角咬缝。 1。 2。 3。 4。 下列有关虚拟团队的叙述,正确的是() 虚拟团队是由某一领域的专家组成。 就时间而言,虚拟团队是短暂的。 虚拟团队有一个领导核心进行管理。 虚拟团队主要依赖电子媒介沟通协调。 Your company has a single Active Directory directory service forest with a forest root domain and a child domain. The child domain is set to the default domain functional level. You install a second domain controller in the child domain by promoting a server named SVR1. You need to rename SVR1 to DC2, and you must ensure that there will be no interruption in the ability of client computers to authenticate to DC2, except during reboot.  What should you do?()   Raise the domain functional level of the child domain to Windows 2000 native. Use System Properties on SVR1 to rename SVR1 to DC2.。  Raise the domain functional level of the child domain to Windows Server 2003. Run the netdom command to rename SVR1 to DC2.。  Raise the domain functional level of the child domain to Windows 2000 native. Run the dcpromo command on SVR1 to remove Active Directory directory service. Use System Properties to rename SVR1 to DC2. Run the dcpromo command to re-install Active Directory.。  Raise the domain functional level of the child domain to Windows Server 2003. Create a DNS CNAME record for DC2.contoso.com that points to SVR1.contoso.com.。 Your company has a network that has an Active Directory domain. The domain has two servers named DC1 and DC2. You plan to collect events from DC2 and transfer them to DC1. You configure the required subscriptions by selecting the Normal option for the Event delivery optimization setting and by using the HTTP protocol. You discover that none of the subscriptions work. You need to ensure that the servers support the event collectors. Which three actions should you perform?() Run the wecutil qc command on DC1.。 Run the wecutil qc command on DC2.。 Run the winrm quickconfig command on DC1.。 Run the winrm quickconfig command on DC2.。 Add the DC2 account to the Administrators group on DC1.。 Add the DC1 account to the Administrators group on DC2.。 感知应对”包括()。 感知。 幽默。 焦虑管理。 选择性觉察。 施工单位编制分部(分项)工程施工组织设计和季、月、旬施工计划的依据是()。
参考答案:

  参考解析

本题考核的是单位工程施工组织设计。单位工程施工组织设计是在施工组织总设计的指导下,由直接组织施工的单位根据施工图设计进行编制,用以直接指导单位工程的施工活动,是施工单位编制分部(分项)工程施工组织设计和季、月、旬施工计划的依据。

在线 客服