当前位置:二建市政工程专业继续教育题库

问题:

[单选] 工程分项的分部分项工程费为400万元。其中,定额人工费为100万元,措施项目费为分部分项工程费的5%,其他项目费为15万元,企业管理费费率为30%,利润率为5%,规费费率为8%,综合计税系数为3.41%。则该工程投标报价中的税金为()万元。

A . 8.00
B . 15.11
C . 20.00
D . 458.11

Where should known problem areas in the site survey be documented?() nowhere (but should be discussed with the customer)。 on the site survey map and within the site survey text。 on the customers blueprints。 in the Cisco WCS Planning Tool。 水平截面 Refer to the exhibit. Users complain that they intermittently lose data and connections to important servers. After investigation, you discover that the 802.1Q trunk between DSW111 and ASW1 is down. Even though the HSRP group 11 is being serviced by DSW112, you discover that the SVI for VLAN 11 is in the up state on DSW111. Which three Cisco Catalyst IOS commands should you use on DSW111 to find the source of this problem? ()(Choose three.) show vtp status。 show interfaces vlan 11。 show standby vlan 11 brief。 show spanning-tree vlan 11。 show interfaces mod/port trunk 。 新闻单位最重要的资源是() 人力资源。 社会声誉资源。 物质资源。 频率(版面)资源。 Which statement best describes the differences between Cisco SMARTnet and Cisco SMARTnet Onsite?()  CiscoSMARTNet Onsite includes all of the elements of Cisco SMARTnet with the additionalprovision of onsite technician to perform parts replacement。  CiscoSMARTnet Onsite is primarily attractive to customers who do not need to replace theirhardware immediately, but would still like an onsite technician to install and replace hardware。  CiscoSMARTnet Onsite includes certification classes and live network consulting at thecustomer site。  CiscoSMARTnet Onsite provides network monitoring for small-to-medium sized businesses andprovides onsite technical resources when hardware problems are detecteD。 工程分项的分部分项工程费为400万元。其中,定额人工费为100万元,措施项目费为分部分项工程费的5%,其他项目费为15万元,企业管理费费率为30%,利润率为5%,规费费率为8%,综合计税系数为3.41%。则该工程投标报价中的税金为()万元。
参考答案:

  参考解析

(400+400*0.05+15+100*0.08)*0.0341=15.11 税金=分部分项工程费+措施项目费+其他项目费+规费(人工费*规费费率)

在线 客服