问题:

[问答题]

某河道工程项目法人按照《水利水电工程标准施工招标文件》(2009年版)编制了施工招标文件,招标文件规定不允许联合体投标。某投标人递交的投标文件由投标函及附录、授权委托书(含法定代表人证明文件)、投标保证金、项目管理机构、施工组织设计、资格审查资料、拟分包情况表、已标价工程量清单组成。投标文件拟将渠道混凝土砌块衬砌项目分包,填报了拟分包情况表。
经评标委员会评审,该投标人中标,并签订合同。施工期第一个月完成的项目和工程量(或费用)如下:
(1)80m3<sup>3</sup>/h挖泥船施工,河道疏浚(5km,断面积48m2);
(2)施工期自然回淤清除(断面积2m2);
(3)河道疏浚超挖断面积(4m2);
(4)排泥管安装拆除,费用10万元;
(5)开工展布,费用4万元;
(6)施工辅助工程,包括浚前扫床和障碍物清除及其他辅助工程,费用50万元。

渠道混凝土砌块衬砌项目分包中,拟分包人须提供的证明材料有哪些?

What affect will a shutdown -Fr command have on the resource groups on a cluster node?() [" They will be placed in an error state."," They will be released an not acquired by another node."," They will migrate to the next node in the priority list."," They will migrate to the next node and be reacquired by the first node on system restart."] 土壤水解性酸 联轴器的作用是什么? A customer has an existing IBM System Storage DS8700 2-way model with 8 mega packs of 300 GB disks and 16 fibre ports.  How many additional fibre ports and mega packs can be installed in the base frame() ["16fibre ports and 0 mega packs","4fibre ports and 8 mega packs","8fibre ports and 4 mega packs","12fibre ports and 0 mega pack"] 可燃气体检测仪的蜂鸣()越高表明气体泄漏浓度越高。 ["幅度","频率","声音","高度"]

某河道工程项目法人按照《水利水电工程标准施工招标文件》(2009年版)编制了施工招标文件,招标文件规定不允许联合体投标。某投标人递交的投标文件由投标函及附录、授权委托书(含法定代表人证明文件)、投标保证金、项目管理机构、施工组织设计、资格审查资料、拟分包情况表、已标价工程量清单组成。投标文件拟将渠道混凝土砌块衬砌项目分包,填报了拟分包情况表。
经评标委员会评审,该投标人中标,并签订合同。施工期第一个月完成的项目和工程量(或费用)如下:
(1)80m3<sup>3</sup>/h挖泥船施工,河道疏浚(5km,断面积48m2);
(2)施工期自然回淤清除(断面积2m2);
(3)河道疏浚超挖断面积(4m2);
(4)排泥管安装拆除,费用10万元;
(5)开工展布,费用4万元;
(6)施工辅助工程,包括浚前扫床和障碍物清除及其他辅助工程,费用50万元。

渠道混凝土砌块衬砌项目分包中,拟分包人须提供的证明材料有哪些?

参考答案:

  参考解析

本题暂无解析