问题:

[单选] 已知某挖土机挖土的一个工作循环需2min,每循环一次挖土0.5m3,工作班的延续时间为8h,时间利用系数K=0.85,则其台班产量定额为()。

A . 12.8m3/台班
B . 15m3/台班
C . 102m3/台班
D . 120m3/台班

You are configuring your computer to use both Windows 2000 Professional and Windows 98. Your computer has 3 6GB hard disks, Disk0, Disk1 and Disk2. You want to configure each hard disk to have a 6GB partition. You want to install Windows 98 on Disk0 and Windows 2000 Professional on Disk1. You want to store your project file on Disk2. You want to implement file level security on Disk1. You want to be able to access your project files when using either operating system. What file system should you implement on each hard disk?   统计规律 地面水泥砂浆整体面层施工后,抗压强度应达到()MPa后,方准上人行走。 20。 15。 10。 5。 FOB(FreeOnBoard船上交货)可能不适合于货物在上船前已经交给承运人的情况,例如用集装箱运输的货物通常是在集装箱码头交货。 You have an Exchange Server 2010 organization.  The network contains two Mailbox servers that are configured in a database availability group (DAG). You plan to implement a disaster recovery solution.  You need to recommend a solution that ensures that the active mailbox database copy is unaffected bythe backup process.  You want to achieve this goal while minimizing costs.  What should you recommend?() Windows Server Backup。 Network Attached Storage (NAS) snapshots。 Microsoft System Center Configuration Manager。 Microsoft System Center Data Protection Manager。 已知某挖土机挖土的一个工作循环需2min,每循环一次挖土0.5m3,工作班的延续时间为8h,时间利用系数K=0.85,则其台班产量定额为()。
参考答案: C

  参考解析

机械产量定额,是指在合理劳动组织与合理使用机械条件下,机械在每个台班时间内,应完成合格产品的数量。则该台班产量定额为:(0.5×480/2)×0.85=102(m3/台班)。

相关题目:

在线 客服