问题:

[单选]

决策树分析方法通常用决策树图表进行分析,很据下表的决策树分析法计算,图中机会节点的预期收益EMV分别是$90和$()(单位:万元)

A . A、160
B . B、150
C . C、140
D . D、100

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has () potential communication channels. A、10。 B、45。 C、50。 D、100。 A () is a collection of projects and other work that are grouped together to facilitate effect -ive management of thatwork to meet strategic business objectives. A、program。 B、portfolio。 C、project of large size。 D、PMO。 Quality planning tools are often used to help plan effective quality management activities.() is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance. A、Benchmarking。 B、Quality metric。 C、Quality checklist。 D、Brainstorming。 某公司现有400万元用于投资甲、乙、丙三个项目,投资额以百万元为单位,已知甲、乙、丙三项投资的可能方案及相应获得的收益如下表所示: 则该公司能够获得的最大收益值是()百万元。 A、17 。 B、18 。 C、20 。 D、21。 某公司从甲地向丁地运送物资,运送过程中先后需要经过乙、丙两个中转站,其中乙中转站可以选择乙1和乙2两个可选地点,丙中转站可以选择丙1、丙2和丙3三个可选地点,各相邻两地之间的距离如表所示,则甲地到丁地之间的最短距离为()。 A、64。 B、74。 C、76。 D、68。

决策树分析方法通常用决策树图表进行分析,很据下表的决策树分析法计算,图中机会节点的预期收益EMV分别是$90和$()(单位:万元)

参考答案:

  参考解析

200*75%+(-40)*25%=140

在线 客服