问题:

[单选] 某工程主体结构混凝土工程量为3200m3,预算单价为550元/m3。计划4个月内均衡完成。开工后,混凝土实际采购价格为560元/m3。施工至第2个月月底,实际累计完成混凝土工程量为1800m3,则此时的进度偏差为()万元。

A . 11.8
B . 11.2
C . 11.0
D . -1.8

继中国移动、中国联通、中国电信之后,谁有望成为第四大运营商?() 以参股方式进入基础电信运营市场的民资企业。 以京东、小米为代表的虚拟运营商。 中国广播电视网络有限公司。 中国铁塔股份有限公司。 While performing a site survey to document the existing environment before implementing a new HACMP cluster, it was discovered that a port filtering firewall was being used to protect the production system. The plan is to continue using the firewall and add a second firewall to avoid a single point of failure. Each node in the two-node cluster will have all of its network adapters connected to the firewalls, and all connections to the nodes will pass through these firewalls.  What must be considered about HACMP in a firewall environment?()    Firewalls are not supported in a HACMP environment.。  HACMP uses only TCP/IP so firewalls are not relevant.。  Specific ports must be open for HACMP communications.。  Dynamic routing must be used to properly route packets in a firewall-protected environment.。 为使车辆分配阀的试验工作程序化、自动化,已研制和使用了()的705型试验台。 数字控制。 微机控制。 油压控制。 电磁控制。 液压油更换方法 A 1500 page print job was sent to the "pcl" queue. The job was running for several minutes before it was determined that the job was not needed. What can be done to delete the job?() kill 201。 cancel 201。 disable pcl。 rm /var/spool/lpd/STDIN.27648。 某工程主体结构混凝土工程量为3200m3,预算单价为550元/m3。计划4个月内均衡完成。开工后,混凝土实际采购价格为560元/m3。施工至第2个月月底,实际累计完成混凝土工程量为1800m3,则此时的进度偏差为()万元。
参考答案:

  参考解析

本题涉及的考点是进度偏差的计算。进度偏差(SV)=已完工作预算费用(BCWP)-计划工作预算费用(BCWS)=已完成工作量×预算单价-计划工作量×预算单价=1800×550-1600×550=110000(元)=11.0(万元)。

在线 客服