[单选] 施工进度计划实施时,将实际数据与进度计划对比之后,应进行的工作是()。

A . 跟踪检查,收集实际进度数据
B . 分析计划执行的情况
C . 检查措施的落实情况
D . 进度计划的变更必须与有关单位和部门及时沟通

《中华人民共和国特种设备安全法》规定:特种设备使用单位在检验合格有效期届满前()向特种设备检验机构提出定期检验的要求。 15天。 1个月。 一个星期。 三个月。 Your company named Contoso, Ltd. has a Network Load Balancing cluster named nlb.contoso.com. The cluster hosts are named WEB1 and WEB2. The cluster is configured with a single port rule that evenly distributes HTTP traffic between both hosts.  You need to configure WEB2 to handle all HTTPS traffic for nlb.contoso.com. You must retain the even distribution of HTTP traffic between WEB1 and WEB2.  Which two actions should you perform?() In the properties for WEB2, change the Handling priority option for the TCP 443 port rule to the value of1.。 In the properties for WEB1, change the Handling priority option for the TCP 443 port rule to the value of 0.。 In the properties for the cluster, create a new port rule for port TCP 443 that has the Filtering mode option set to Single host.。 In the properties for the cluster, create a new port rule for port TCP 443 that has the Filtering mode option set to Multiple host and the Affinity option set to the value of Single.。 评估机构在制定绩效评价方案时,应当有针对性地对项目所涉及的利益相关方开展各种形式的调查,其调查方法包括()。 A.案卷研究 。 B.数据填报 。 C.实地调研 。 D.座谈会及问卷调查。 前摄抑制 Your company has an Active Directory Domain Services (AD DS) domain. You install the Remote Desktop Session Host (RD Session Host) role service on a server that runs Windows Server 2008 R2. All RD Session Host servers are located in an Organizational Unit (OU) named RDSessionHosts. All user accounts are located in an OU named Employees. Users connect to multiple RD Session Host servers by using the Remote Desktop Connection client on their Windows 7 client computers. You need to ensure that users can access the files stored in their own Documents folders regardless of the RD Session Host server to which they are connected. What should you do?() Create a mandatory profile on each client computer.。 Create a mandatory profile on each RD Session Host server.。 Create a Group Policy object (GPO) that redirects the Documents folder, and link the GPO to the Employees OU.。 Create a Group Policy object (GPO) that redirects the Documents folder, and link the GPO to the RDSessionHosts OU.。 施工进度计划实施时,将实际数据与进度计划对比之后,应进行的工作是()。
参考答案:

  参考解析

施工进度计划实施的过程:①跟踪检查,收集实际进度数据;②将实际数据与进度计划对比;③分析计划执行的情况;④对产生的进度变化,采取措施予以纠正或调整计划;⑤检查措施的落实情况;⑥进度计划的变更必须与有关单位和部门及时沟通。

相关题目:

在线 客服