[单选] 下面关于无粘结预应力的施工,说法正确的是()。

A . 在预应力混凝土楼盖中的张拉顺序是先张拉楼面粱、后张拉楼板
B . 板中的无粘结预应力筋应同时对称张拉
C . 梁中的无粘结预应力筋应依次张拉
D . 正式张拉之前,宜用千斤顶将无粘结预应力筋先往复抽动1~2次后再张拉

叙述好氧堆肥的机理。参与堆肥发酵的微生物都有哪些? A University customer has a BladeCenter H fully populated with LS21 Blades, a single AMM, and four power modules. The BladeCenter has been running flawlessly for three months. One day an administrator discovers that they cannot view video on blades 9-12 either locally or remotely even though they still appear to be running. The video works on all of the other blades. Which of the following is the cause of the video problem?() A power module has failed and there is not enough power to see video on all blades.。 MUX 3 on theBladeCenter backplane has failed.。 A firmware update is required on the AMM.。 A second AMM is required to view video on blades 9-14.。 除盐系统废水中和至合格后才可排放,排放要求的PH值为() 6—9。 4—6。 9—11。 Which of the following products and utilities can be used to update all encrypted data as well as the merchant key in a WebSphere Commerce database for a given instance?() The Database Update Tool found in Configuration Manager。 The LDAP Server。 The WebSphere Application Server Administrative Console。 The WebSphere Commerce SecurityUpdate Command。 The WebSphere Commerce Administration Console。 折叠式封堵头用于含硫化氢物质的封堵后,应() 检查密封件情况,判断能否继续使用。 更换全部紧固件。 更换全部密封件。 封堵头不能使用。 下面关于无粘结预应力的施工,说法正确的是()。
参考答案:

  参考解析

无粘结预应力筋的张拉应严格按设计要求进行。通常,在预应力混凝土楼盖中的张拉川页序是先张拉楼板、后张拉楼面梁。板中的无粘结预应力筋可依次张拉,梁中的无粘结预应力筋可对称张拉(两端张拉或分段张拉)。正式张拉之前,宜用千斤顶将无粘结预应力筋先往复抽动1~2次后再张拉,以降低摩阻力。故本题答案为“D”。

在线 客服