问题:

[单选]

施工组织总设计包括如下工作:()。
①计算主要工种工程的工作量;
②编制施工总进度计划;
③编制资源需求量计划;
④拟定施工方案。其正确的工作顺序是

A . ①②③④
B . ①④②③
C . ①③②④
D . ④①②③

Your company has a network that has an active directory domain. The domain has two servers named DC1 and DC2. You plan to collect events from DC2 and transfer them to DC1. You configure the required subscriptions by selecting the normal option for the event delivery optimiation setting and using the HTTP protocol. you discovere that none of the subscritpions work. You need to ensure that the servers support event collectiors.  which three actions should you perform()?    Run the wecutil qc command on DC1。 Run the wecutil qc command on DC2。 Run the winrm quickconfig command on DC1。 run the winrm quickconfig command on DC2。 Add the DC2 account to the administrators group on DC1。 Add the DC1 account o the administrators group on DC2。 You work as the enterprise exchange administrator at TestKing.com. TestKing.com makes use of Microsoft Exchange Server messaging solution. The TestKing.com network consists of a single Active Directory domain named testking.com. TestKing.com is configured to run in an Exchange Server 2010 environment. You have received instructions from the CIO to deploy a public access solution. To accomplish this task you need to ensure that the admin department is able to send e-mail messages to public folders as well as prohibiting themfrom using Outlook Web App (OWA) to read any document in the public folders. What should you do?() This can be achieved by using OWA segmenttation and Send As permissions.。 This can be achieved by using using mail-enabled public folders and Editor permissions.。 This can be achieved by using  using mail-enabled public folders and Contributor permissions.。 This can be achieved by using OWA segmentation and Reviewer permissions.。 狭义的发展经济学 我国社会必然要经历一个很长的社会主义初级阶段的必然性是因为:() 生产力的落后状况决定的。 商品经济不发达决定的。 社会主义改造时间短决定的。 大跃进、人民公社的历史决定的。 我国长期没有实行对外开放决定的。 You are designing a strategy to meet the security and financial requirements related to the Manifest application.  What should you do? ()  Configure a VPN server in Sydney.。  Configure a VPN server in each branch office.。  Configure a dial-up server in Sydney。  Configure a dial-up server in each branch office.。

施工组织总设计包括如下工作:()。
①计算主要工种工程的工作量;
②编制施工总进度计划;
③编制资源需求量计划;
④拟定施工方案。其正确的工作顺序是

参考答案:

  参考解析

施工组织总设计的编制通常采用如下程序:(1)收集和熟悉编制施工组织总设计所需的有关资料和图纸,进行项目特点和施工条件的调查研究;(2)计算主要工种工程的工程量;(3)确定施工的总体部署;(4)拟订施工方案;(5)编制施工总进度计划;(6)编制资源需求量计划;(7)编制施工准备工作计划;(8)施工总平面图设计;(9)计算主要技术经济指标。因此本题正确答案为B。

相关题目:

在线 客服